FS#8082 — FS#11956 — Powering BHS1/BHS2

Attached to Project— Datacenters
Maintenance
Beauharnois
CLOSED
100%
This Wednesday, November 5th, 2014, we will run several tests of electric switch in order to validate the performance of the generator GE2.

No cut-offs expected, generators and UPS will take over during the various tests.
Date:  Monday, 17 November 2014, 14:33PM
Reason for closing:  Done