FS#7364 — FS#11253 — RBX <> TH2

Attached to Project— Network
Maintenance
Whole Network
CLOSED
100%
Maintenance is taking place on the amplifier site in Nogent on the fibre cable between Roubaix and Paris - Telehouse 2.

The power equaliser is not operating correctly. We are going to reboot it and possibly replace it.

No impact on traffic is expected. The protection in GSW will take over.
Date:  Thursday, 24 July 2014, 16:38PM
Reason for closing:  Done
Comment by OVH - Thursday, 24 July 2014, 15:02PM

We're replacing the equaliser.


Comment by OVH - Thursday, 24 July 2014, 15:03PM

Circuit protection is currently going via GSW.


Comment by OVH - Thursday, 24 July 2014, 15:08PM

Th card has been replaced and the OCG cable between Roubaix and TH2 is back up. However, traffic will continue to be routed via GSW.

We will control with the TAC if everything goes OK.


Comment by OVH - Thursday, 24 July 2014, 16:38PM

Intervention is complete. The TAC has validated the implementation of the new card.