We have detected a potential failure on the electrical supply of few servers SP1.
In order to proceed to the replacement of the power supply, we are planning a maintenance within 10 minutes.
Concerned customers will receive an email precising the date of this maintenance.
Date: Tuesday, 28 May 2013, 08:00AMIn order to proceed to the replacement of the power supply, we are planning a maintenance within 10 minutes.
Concerned customers will receive an email precising the date of this maintenance.
Reason for closing: Done
We are starting with the rack T01C01
Rack T01C01 is done
We moved to the racks T01C02 T01C03 T01C04
Racks T01C05 T01C06 T01C07 in progress
It is done.