bru-1 done.
vss-3 in progress.
vss-3 accomplished. we're dealing with rbx-99
rbx-99 almost done. we're dealing with vss-1
vss-1 done. we're dealing with vss-2
done. all routers at roubaix has been switched on an intermediate configuration (until the arrival of ASR).
we are enabling roubaix/london http://status.ovh.co.uk/?do=details&id=246 to see what will happen to routers.
It is properly enabled. no problem is detecetd. we are going to wait Monday night's task on roubaix/Brussels in order to check the network's behaviour thereafter an expected disconnection ... http://status.ovh.co.uk/?do=details&id=285
Powered by Flyspray OVH RSS
bru-1 done.
vss-3 in progress.
vss-3 accomplished.
we're dealing with rbx-99
rbx-99 almost done.
we're dealing with vss-1
vss-1 done.
we're dealing with vss-2
done.
all routers at roubaix has been switched on an intermediate configuration (until the arrival of ASR).
we are enabling roubaix/london
http://status.ovh.co.uk/?do=details&id=246
to see what will happen to routers.
It is properly enabled. no problem is detecetd.
we are going to wait Monday night's task on roubaix/Brussels in order to check the network's behaviour thereafter an expected disconnection ...
http://status.ovh.co.uk/?do=details&id=285