FS#2656 — FS#6614 — Marseille optical loop : set up of CAV13
Attached to Project— ADSL / SDSL
Modernization | |
Backend / Core | |
CLOSED | |
![]() |
We intervene tomorrow on the optical loop #1 composed of the NRAs :
JOL13, FER13, COR13, DRA13, PRA13, SMG13, STM13, SML13, BEA13, MEN13, GAR13, NAP13
We set up the NRA CAV13 and we finalise the securisation working of the loop.
The workings are expected to take place the whole day from 9:00 to 18:00.
No interruption is expected on the NRAs which are already in production.
Date: Saturday, 21 April 2012, 03:16AMJOL13, FER13, COR13, DRA13, PRA13, SMG13, STM13, SML13, BEA13, MEN13, GAR13, NAP13
We set up the NRA CAV13 and we finalise the securisation working of the loop.
The workings are expected to take place the whole day from 9:00 to 18:00.
No interruption is expected on the NRAs which are already in production.
Reason for closing: Done