FS#6616 — Lille dslam loop
Scheduled Maintenance Report for Web Cloud
Completed
We are migrating the escalations of the router 6k to the 2 n5.


This afternoon, we are going to interrupt a side to plug it on the fisrt n5.


Tomorrow morning at 7:00, we are going to do a shutdown on the ports on the 6k
and to mount them on the n5. It is expected to have 1 minute of interruption. No synchronisation
of adsl/sdsl.

We are going to see if everything is ok. In case of problems, a roll back in 1 minute
is posible.

Tomorow during the day, we will unplug the interrupted side of 6k in order
to put the second n5 and we put on the securisation.

Update(s):

Date: 2012-04-21 00:54:57 UTC
A problem in the garter.
All NRA in Lille are secured on the 2 n5.


Date: 2012-04-21 00:53:23 UTC
Ports are up on the 2nd n5.
A single port is not yet mounted, we are checking the link physically.


Date: 2012-04-21 00:51:43 UTC
We are starting to switch to the 2nd nexus and engage security.



Date: 2012-04-21 00:50:58 UTC
We are ending switching tasks this afternoon. We are going to re-cable the rest of the fibres on the second nexus. Tonight at 00h00 we are engaging security.


Date: 2012-04-20 14:21:17 UTC
migration successfully completed, customers can ping nexus.

Date: 2012-04-20 14:00:45 UTC
We will proceed to cutting off the port-channel and the interface on 6K then switch towards nexus.



Date: 2012-04-19 18:25:17 UTC
We are going to interrupt a side on 6k.
Posted Apr 19, 2012 - 18:24 UTC