FS#1986 — FS#5909 — Lille loop 2 (HEL59,TRI59, ASQ59, LZI59,LQN59)- 20/10/11
Attached to Project— ADSL / SDSL
Maintenance | |
Backend / Core | |
CLOSED | |
![]() |
We will intervene on the loop 2 for security works (same as what has been done on the Loop 1, see task # 5763). This involves a migration of DSLAMs uplinks to a new transportation equipment. So there will be a cut off for the service on each successive NRA,we will try to minimize it as much as we can.
We planned a maintenance window of 1 hour by NRA, knowing that the effective cut off should not take more than few minutes. Work will begin around 22:00. The NRAs will be impacted in the following order: HEL59, TRI59, ASQ59, LZI59, LQN59.
Date: Wednesday, 26 October 2011, 00:31AMWe planned a maintenance window of 1 hour by NRA, knowing that the effective cut off should not take more than few minutes. Work will begin around 22:00. The NRAs will be impacted in the following order: HEL59, TRI59, ASQ59, LZI59, LQN59.
Reason for closing: Done
Securing works begin tonight at 22:00. We will migrate the following sites: HEL59, TRI59 and ASC59.
Works are ongoing, we are preparing the switchnig on HEL59.
We are switching HEL59.
HEL59 switched,we are preparing the switching of TRI59.
TRI59 switched,we are preparing the link TRI<>ASC.
Our optical equipment is up on ASC but the link is not prodable, there is an amp to settle. We will not switch ASC tonight.
Works completed. We will continue in a few days with some failovers for ASC, LZI and LQN.
We will continue the maintenance tasks tonight starting from 22:00. Expected switch of NRAs ASC, LZI and LQN.
We will switch ASC59.
ASC59 switched.
We will switch LZI59.
LZI59 switched. We prepare for the switch of LQN59.
LQN switched.