FS#170 — FS#4259 — Reboot of the level 2 switches
Attached to Project— Dedicated servers
Maintenance | |
all (dedicated servers) | |
CLOSED | |
![]() |
We will perform the updating of the level 2
switching equipment.
This operation will be done at night, between 01h and 07h in the morning
from Tuesday, 08/06/2010 until Friday
11/06. It will cause a network interruption of approximately 3 minutes
on each network of dedicated servers.
Date: Wednesday, 16 June 2010, 17:19PMswitching equipment.
This operation will be done at night, between 01h and 07h in the morning
from Tuesday, 08/06/2010 until Friday
11/06. It will cause a network interruption of approximately 3 minutes
on each network of dedicated servers.
Reason for closing: Done
We will start reboots of switches this night.
Operations will continue tonight.
we still have two more switches to update.
The operation will be done during Friday night 11 until Saturday 12 at about 4 am.
Here are the concerned networks:
188.165.192.0/24
188.165.193.0/24