Last week two new routers have been installed in our Sydney Datacenter in order to improve the network. The main targets of these routers are to connect more providers to help the connectivity to our customers.
Before to connect new providers, we need first to migrate the actual ones to these new routers. This maintenance is scheduled the 5th of Decembre (01:00PM UTC - 00:00 Sydney time)
Date: 2017-12-11 04:54:16 UTC Port is now up and running. Traffic is load-balanced between both links
We will continue to monitor
Date: 2017-12-06 17:18:11 UTC We don't have a good light level with TELSTRA. We have open a trouble ticket with them to troubleshoot.
The traffic is going using the second link.
Date: 2017-12-06 16:40:38 UTC We have proded IX AUS.
We don't see any CRC and the traffic seams to be as before the migration.
Date: 2017-12-06 13:24:50 UTC We isolate IX AUS and the second port TELSTRA
Date: 2017-12-05 13:35:03 UTC We will migrate IX AUS and the second port TELSTRA on syd-sy2-bb1-a9 the 6th of Decembre (01:00PM UTC - 00:00 Sydney time)
Date: 2017-12-05 12:35:34 UTC Equinix is correctly moved.
Date: 2017-12-05 11:53:03 UTC We start to isolate Equinix, the traffic will be redirect during the change