FS#15122 — bhs2-16ab-n56
Attached to Project— Network
Planned Work | |
Beauharnois → BHS-4 | |
CLOSED | |
![]() |
Intervention date between 26 of October 08:00 AM and 10:00 UTC
We have CRC on one of the VPC links of this pair of n56, we will clean the optical fiber and replace the SFP modules if necessary.
No impact to predict the link is redundant.
Thank you for your understanding.
Date: Thursday, 26 October 2017, 08:28AMWe have CRC on one of the VPC links of this pair of n56, we will clean the optical fiber and replace the SFP modules if necessary.
No impact to predict the link is redundant.
Thank you for your understanding.
Reason for closing: Done
Additional comments about closing: Fiber cleanned no more CRC.
No impact.
We are currently cleaning the fiber.
The vPC interface Ethernet 1/47 is currently shutted. No impact a vPC link is still up.