FS#15113 — G103B16, G103B18, G104A03, G104A04, G104B06, G104B09

Attached to Project— Network
Modernization
Gravelines   → GRA-1
CLOSED
100%
Summary: As we are continuously improving the quality of our systems, we will be upgrading our public facing network equipment to a superior model
Actions: Replace the public network device.
Start: Monday 30 October 2017. starting at 10:00 PM (UTC +02)
Affected racks: G103B16, G103B18, G104A03, G104A04, G104B06, G104B09
Impact: One disconnection of about one minute of the public network.
This task will be updated regularly during the maintenance
Date:  Tuesday, 31 October 2017, 04:51AM
Reason for closing:  Done
Comment by OVH - Monday, 30 October 2017, 22:04PM

The migration of equipments for racks G104B06 and G104B09 to be begun


Comment by OVH - Monday, 30 October 2017, 22:06PM

The migration of equipments for racks G103B16 and G103B18 to be begun


Comment by OVH - Monday, 30 October 2017, 22:15PM

The migration of equipments for racks G104A03 and G104A04 to be begun


Comment by OVH - Monday, 30 October 2017, 23:47PM

The migration of the racks G104A04 is ended.


Comment by OVH - Tuesday, 31 October 2017, 00:37AM

The migration of equipments for racks G103B16, G103B18, G104A03, G104B06, G104B09 are ended, we proceed to the last checks.


Comment by OVH - Tuesday, 31 October 2017, 00:39AM

The migration of equipments for racks G103B16, G103B18, G104A03 are ended.


Comment by OVH - Tuesday, 31 October 2017, 04:51AM

The migration of equipments for racks G104B06, G104B09 are ended.