FS#14828 — G128/G137

Attached to Project— Datacenters
Maintenance
Gravelines
CLOSED
100%
Summary : We will switch the cooling on the definitive dry-cooler
Actions : switching to definitive dry-cooler
Start : 10/07/2017 at 10:00 AM
Affected Rack : G128 / G137
Impact : None
Estimated Time : 10/07/2017 at 4:00 PM
Date:  Sunday, 23 July 2017, 17:57PM
Reason for closing:  Done
Comment by OVH - Monday, 10 July 2017, 10:14AM

In progress


Comment by OVH - Thursday, 13 July 2017, 13:52PM

A new intervention is necessary. It will be done on Monday 17th starting at 10:00AM

No impact expected.