FS#14691 — FS#25223 — Rack: 23A03
Attached to Project— Datacenters
Maintenance | |
Roubaix 2 | |
CLOSED | |
![]() |
Summary : We have detected a fault on part of the Cooling System of this rack.
Actions : Replacement of the defective part(s).
Start : tuesday june 13th 2017, 10h
Affected Rack : 23A03
Impact : None.
Estimated Time : we will update the task
Date: Tuesday, 13 June 2017, 17:30PMActions : Replacement of the defective part(s).
Start : tuesday june 13th 2017, 10h
Affected Rack : 23A03
Impact : None.
Estimated Time : we will update the task
Reason for closing: Done
Intervention is started
Intervention done