FS#14596 — G113A15 ; G113A16 ; G113A24 ; G113A25 ; G113B16 ; G113B21
Attached to Project— Network
Modernization | |
GRA-1 | |
Planned | |
![]() |
Summary: As we are continuously improving the quality of our systems, we will be upgrading our public facing network equipment to a superior model
Actions: Replace the public network device.
Start: 23/05/17 starting at 10:00 PM (UTC +02)
Affected racks: G113A15 ; G113A16 ; G113A24 ; G113A25 ; G113B16 ; G113B21
Impact: One disconnection of about one minute of the public network.
This task will be updated regularly during the maintenance
Actions: Replace the public network device.
Start: 23/05/17 starting at 10:00 PM (UTC +02)
Affected racks: G113A15 ; G113A16 ; G113A24 ; G113A25 ; G113B16 ; G113B21
Impact: One disconnection of about one minute of the public network.
This task will be updated regularly during the maintenance
The maintenance is started for the Rack G113A15.
Maintenance is still ongoing. We are going to update you every hour.
Maintenance is still on-going. Thank you for your patience.
We stop the maintenance for now. It will continue tomorrow at 10pm FR time.
Maintenance re-started around 60mn ago.
We will keep you updated on the evolution.
Thank you for your comprehension.
We have completed the following racks:
G113A24 ; G113A25 ; G113B16 ; G113B21
Next rack will be done next Monday.
Thank you for your patience.