FS#1144 — FS#5152 — RBX2 : adjustment of the EDF protection

Attached to Project— Datacenters
Modernization
Roubaix 2
CLOSED
100%
We will do tomorrow an adjustment of the principal protection for the RBX2 datacenter.

During the time of adjustment and tests, we will siwtch the load of the datacenter to generators.

It will be done at 10 o'clock.


Date:  Wednesday, 16 February 2011, 12:06PM
Reason for closing:  Done
Additional comments about closing:  Switching to generators and setting of protection have been made.