FS#10731 — FS#14593 - Power Supply

Attached to Project— Datacenters
Maintenance
Beauharnois
CLOSED
100%
From September 8th to 11th, we're planning an intervention on our 120KB workstation. One of the lines supplying the datacentre will be out of service.
During this maintenance, the site will be supplied by the other electricity supply and backed up by the generators.
Date:  Wednesday, 25 May 2016, 10:26AM
Reason for closing:  Done